Earned Value Analysis :Cost Variance

Earned Value Analysis is a Cost Control Tool/Technique. For a project manager Earned Value gives an idea on what you have achieved for the amount of money you spent. The main calculations in EV techniques are

1. Cost Variance : Compares Cost with budget

Cost Variance = Earned Value - Actual Cost

CV = EV - AC

If your Earned Value = 1000 and your Actual Cost is 900, your Cost Variance is 100. In this case CV is a positive number and you are running with in the budget or spending less than what you have budgeted. Instead of 900, if your actual cost is 1100, your Cost Variance is -100. In this case you have to be careful and check your spending against plan.



http://www.ajithn.com/

For Free PMP Exam preparation tests

Risk Identification : Tools & Techniques - SWOT

Strength, Weakness, Opportunities and Threats (SWOT) analysis is a technique to systematically analyse the project,processes,resources, organization etc. Your focus will be on finding the S,W, O or T in each of these area. It is part of Tools & Technique section of Risk Identification

http://www.ajithn.com/
Your companion in PMP preparation

Friday, December 28, 2007

How to pass PMP Examination

To pass PMP examination, you have to read the PMBOK thoroughly. But this will not ensure that you will pass the exam. You need to practice PMP questions.
One site which will be useful for PMP exam practice is
http://www.ajithn.com/
You can take unlimited number of trials. There are over 100 questions which check your understanding of PMBOK and there are many real life PMP questions